District weighs seed, sod and turf for middle-school fields; contractor to deliver alternative costs for November
Summary
The district’s five-year facilities plan lists $1.265M to regrade and renew middle-school athletic fields. Staff will collect line-item contractor bids (seed, sod, turf options and a new softball field) and expects to report numbers in November; athletics director Sarah Oswald said turf would expand practice and scheduling options but has lifecycle costs.
Administration told the operations committee that the district’s five‑year facilities plan lists $1.265 million to renovate the middle‑school athletic fields, including regrading, seeding or sodding, and construction of a new softball practice field and backstop fencing.
The MFP figure includes design and consultant fees. Staff said seeding would reduce upfront costs by about $350,000 compared with sodding but would leave the fields unusable for up to two years while grass established. Sodding is more…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat