Summary
The township has proposed a joint installation of new vehicle fueling tanks at a property it bought; the district could remove its underground tanks and rely on township pumps. Officials said costs, cost‑share percentages and environmental‑liability questions remain under study and numbers should be available in about a month.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The committee heard a preliminary update on a township plan to build a new fueling system on the former McAuliffe property and asked whether the school district would be interested in sharing use and costs.
Administration said the township’s Department of Public Works is evaluating removing the district’s underground tanks and installing new pumps on their property. "We remove everything from underneath our ground, and we never have to worry about another leak," said a district staff member discussing the potential environmental benefit of relying on the township’s system.
Officials said the discussions are at an early stage: the township is doing cost work on removing its system, installing a new system and removing the district’s tanks. The district currently operates one 3,000‑gallon gasoline underground tank and a 9,000‑gallon diesel tank at the bus garage. Administration expects a set of preliminary cost numbers in about a month and stressed that any joint work would be subject to the township’s board process and further district review.
There was no action taken at the meeting; staff said they will return with numbers when they are available.
What happens next: The township is completing cost estimates for removing and replacing tanks and pumping infrastructure; the district expects preliminary numbers in roughly a month and will evaluate procurement, operational impacts for the bus company, and environmental‑liability issues before any commitment.