Get AI Briefings, Transcripts & Alerts on Local & National Government Meetings — Forever.
Generation180 outlines solar feasibility for Oley Valley SD and urges application for state grant
Summary
A nonprofit and contractors presented a rooftop solar feasibility study showing a ~1–3 MW option for Oley Valley SD, estimated capital costs of roughly $2.1–$2.2 million before incentives, and recommended applying for the Solar for Schools state grant by mid‑February to preserve federal tax credit eligibility.
Shannon Crooker of Generation180 presented a free feasibility study to the Oley Valley School District board on Jan. 20, outlining rooftop solar options for the high school and middle school and urging the district to apply for a state Solar for Schools grant. Crooker said the high school rooftop could offset roughly 100% of its electricity and that combined projects would increase economies of scale.
Why it matters: Crooker said federal and state incentives significantly change the economics and that timing is critical because the federal Investment Tax Credit (ITC) is being revised. “It has to make sense for you financially. It has to be a good fit for you both from an educational and budget standpoint,” Crooker said, underscoring that her nonprofit provides analysis and grant writing assistance funded by the Berks County Community Foundation.
The study presented a full project cash price in the $2.1 million–$2.155 million range (about $2 per watt in a single‑school scenario), and Crooker estimated the ITC (about 30% of project cost) plus the state Solar for Schools grant (up to $360,000 or 30%, whichever is less) would reduce net capital exposure. She also noted a projected first‑year SRAC (solar renewable energy credit) revenue stream and estimated a 12‑year simple payback and a 6.7% internal rate of return under the cash/lease model shown to the board.
Contractor and financing details: Jackson Kuziak of Solar Possible, who worked on the financial model, told the board the stated IRR spreads one‑time incentives over a 25‑year analysis and is calculated on the lease structure proposed; the model assumes annual electric savings plus SRAC revenue of roughly $100,000 a year. Sean Corrigan of First American explained a 7‑year lease finance option that would fund construction, put funds in escrow to pay vendors, and then require annual lease payments; Corrigan said the ITC and grant dollars would be applied against the third annual lease payment in the conservative schedule shown.
Board questions and risks: Board members pressed on whether the IRR used gross cost or net incentives, grid interconnection feasibility, the difference between owning the system and third‑party ownership (PPA), and the durability of incentives. Kuziak said preliminary analysis found no immediate transformer or substation constraints but that MetEd (the utility) requires stamped engineering plans before confirming full interconnection capacity. Crooker and Kuziak warned of new procurement restrictions tied to foreign‑entity rules that could affect equipment sourcing and third‑party interest, and they recommended contract provisions that condition obligations on receiving the ITC to limit district exposure.
Cost and operations: Crooker presented combined‑project scenarios that lower the per‑watt installed cost (to about $1.82/W in a combined bid) and increase annual savings (roughly $130,000/year combined in the model) while also raising operations and maintenance estimates (examples shown: about $7,400–$11,000 per year depending on scope). She said roof condition matters: some roofs (elementary school example) may need replacement before solar installation, which changes timing and costs.
Next steps: Crooker recommended the district submit a simple board resolution to apply for the Solar for Schools grant (a template that assigns two board members to sign the grant agreement if awarded) and suggested a submission target of roughly Feb. 20 so the Commonwealth Financing Authority can consider awards at its March meeting. The board did not vote to commit to construction; several members said there is no financial risk to applying and supported taking the step to submit paperwork at the February voting meeting, but a final board decision on any contract would happen later.
What remains unresolved: Timing and formal guidance for certain ITC rule changes remain pending; Crooker said federal guidance has been delayed and that there is some risk the credit could change if procurement rules are not met. Interconnection approvals from MetEd require stamped engineering plans, and the district would need to confirm roof readiness and precise meter/site configurations before final design.
The board agreed to pursue further information and to consider a resolution at its Feb. 17 voting meeting to preserve the grant opportunity.

