Board approves retroactive change order for athletic lights after conduit damage; project $3,071 over budget
Summary
Board members described storm damage to underground conduit and approved a retroactive change order to reroute power for athletic field lighting. The reroute increases the project by $3,071.13; staff will ask insurance but said proof the storm caused the damage may be difficult.
The board discussed a retroactive change order to keep the athletic field lighting project on schedule after staff discovered crushed underground conduit during storm‑damage repairs.
Facilities staff described efforts to pull wiring through an existing conduit; when crews could not get through, they approved a change to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat