Board approves retroactive change order for athletic lights after conduit damage; project $3,071 over budget
Summary
Board members described storm damage to underground conduit and approved a retroactive change order to reroute power for athletic field lighting. The reroute increases the project by $3,071.13; staff will ask insurance but said proof the storm caused the damage may be difficult.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board discussed a retroactive change order to keep the athletic field lighting project on schedule after staff discovered crushed underground conduit during storm‑damage repairs.
Facilities staff described efforts to pull wiring through an existing conduit; when crews could not get through, they approved a change to route power to a different panel near the concession/restroom area so lights could be energized. Secretary/Facilities (S4) told the board the change will increase the project cost by $3,071.13 and said contingency funds exist to absorb the overrun.
Board members asked whether the district could submit the cost to insurance; staff said they could inquire but cautioned there may be no way to prove the storm caused the crush and that contractors who drilled or later moved debris might bear responsibility. "I don't feel good about them covering that, but I can ask," the facilities speaker said. Another board member noted that if a contractor drilled near marked lines and damaged them, that contractor could be responsible.
The board agreed to proceed with the reroute to keep the lighting project moving and planned to follow up with the contractor and insurer to explore possible reimbursement.
The board indicated it will retroactively approve the change order at its next meeting.