Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Contracts Grants Construction topic
No spam. Unsubscribe anytime.
Board approves stadium change order and a consulting agreement for state facility grant; Delta contract passes amid two dissenting votes
Summary
The Millersburg board approved a stadium change order adding a second ADA ramp after borough code enforcement required it and approved a contract with Delta to pursue a DCEE facility-improvement grant (asbestos abatement and window replacement). The Delta agreement passed with two 'No' votes (Miller, Peterson).
Get email alerts on the Contracts Grants Construction topic
No spam. Unsubscribe anytime.
The board approved several operational contracts and a construction change order during the meeting.
Stadium construction: The board approved a change order from Stadium Solutions that adds a second ADA ramp to the bleacher scope at the borough's request (one ramp on each side). Administration explained that a sidewalk deduct was included so six track lanes could fit; the district's solicitor advised that a variance was unlikely, so the change order was adopted to keep the project moving. Administration said the construction schedule remains aggressive, with March 20 as a target completion date but with risk that shipping or approvals could delay parts of the work. Athletic director Damon and facilities staff said contingency plans for a late March track meet were being developed.
DCEE facility grant and consultant agreement: Administration said it plans to apply for a state DCEE facility-improvement grant (priority projects: asbestos abatement in the high-school auditorium floor tile/mastic and window replacement of 1972 single-pane units). Because the application deadline was mid-March, the board first voted to amend the agenda to consider approval of an agreement with Delta (a grant consultant the district has used previously). The agreement as discussed included a $5,000 minimum engagement fee and a contingent 1% fee on any awarded funds. Supporters noted Delta's prior work on environmental studies and contacts in state agencies; some members cautioned that prior engagements had not yet produced award wins for all projects. The board voted to approve the Delta agreement by roll call: Eggleston—Yes; Enders—Yes; Hersey—Yes; Miller—No; Peterson—No; Shutt—Yes; Minnick—Yes.
Other contract and administrative votes at the meeting included approval of a revised agreement with Century New Century Inc. and the donation of outdated kitchenware to Valley Lighthouse; both passed by roll call.
Next steps: Administration will proceed with the DCEE application materials and coordinate construction timelines for the stadium project, keeping the board informed of any impacts to scheduled events.

