Chiliquin gym delayed by weather and archaeological holds; Bonanza gym costs and other facility projects reviewed
Summary
District staff reported construction progress and delays on the Chiliquin gym, summarized final costs for the Bonanza gym and gave updates on Lost River Community Center, Crater Lake Learning Center and the Kino seismic project. Administrators said some projects were advanced with ESSER funds and that artifacts and weather caused schedule slips.
District construction and facilities staff updated the budget committee on multiple capital projects during the meeting, including the Chiliquin gym, the recently completed Bonanza gym and other reserve-account projects funded with ESSER and local construction reserves.
S3 (Director of Business Services) said the Chiliquin gym contract with Diversified is for about $5.999 million and that, as of May 2, the district had spent $3.2 million. Work faced weather-related delays and periodic holds for archaeological artifact monitoring, pushing occupancy targets into August. “As of May 2, we've…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat