District outlines demolition, salvage plans and community outreach for high school rebuild
Summary
Banks SD 13 told the board demolition crews and large equipment are expected Dec. 15 with demo work after students leave Dec. 20; the district will publish a salvage list, post a newsletter to ~3,000 emails and hold a community meeting Feb. 3.
Get email alerts on the Construction Timeline topic
No spam. Unsubscribe anytime.
Speaker 3 (Presenter) informed the board that planning commission approval and an early grading permit are in place and that large equipment is expected on Dec. 15. Significant demolition of the South Wing, the former admin center and the barn is scheduled for late December through February, with an anticipated early-February completion of the demo phase.
The district will carry out abatement, wall shoring and salvage operations once spaces are vacated. Speaker 6 (Staff member) said the team has identified items for salvage — including the gym floor and district-office flooring — and will share a detailed list with the community once cost estimates are finalized.
“We actually have all of the items that are gonna going to be salvaged,” Speaker 6 said, and added staff will coordinate the traditions and innovation committee to determine placement of salvaged pieces in the new school.
Communications plans: Speaker 3 said the district will send a newsletter on Dec. 12 to about 3,000 email addresses, publish a social-media kickoff post the following Monday, and distribute a letter from the district and high school about logistics for families. A bond oversight committee meeting is set for Dec. 16 and a community meeting for Feb. 3.
Community concerns and logistics: Speaker 7 urged clearer web navigation — suggesting replacing or supplementing the word “bond” with “construction” and adding a prominent banner so residents can quickly find project details online. Board members and staff also discussed event logistics (restroom trailers, parking and spectator access) while construction is underway.
What remains to be finalized: the cost estimates for salvaged items, exact dates for some early bids, and neighborhood communications for events and demo vibration impacts. Staff committed to producing and publishing the salvage list and to follow up on site-specific logistics and safety communications.