Board told one high‑school chiller has failed; staff recommend using pre‑bid contract to speed repair
Summary
Operations staff told the board one of two chillers at the high school has rusted internally and recommended using an existing RFP (OSC) to avoid supply delays; a revised proposal reduced the estimate from about $115,000 to roughly $99,000–$100,000 and staff asked to return Jan. 7 for approval.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
District operations staff told the Coventry Local School Board on Dec. 17 that one of two chillers controlling the high school’s air conditioning has deteriorated and needs replacement. The district has one functioning chiller but the second unit has "rusted out" internally and is not repairable, staff said.
Operations staff presented two procurement options: run a new RFP locally and face multi‑month lead times, or use an OSC‑procured proposal (a contract the high school council vetted on behalf of members) to shorten the schedule. The superintendent’s operations contact said a new RFP would likely push ordering into February with a three‑to‑four month lead time, risking delayed summer completion; using the OSC procurement could secure parts earlier.
Staff reported they negotiated a revised equipment plan that reduced costs from about $115,000 to roughly $99,000–$100,000, noting a $15,000 savings from the earlier estimate. They asked the board to authorize bringing a formal contract back for approval at the Jan. 7 meeting so work could be scheduled for early June.
Board members discussed the timing and supported returning the recommendation in January. No contract was approved Dec. 17; the board will consider the formal procurement and vote in January when the proposal is presented for approval.