Troy City School District board hears update on $56M modernization; tech wing delayed by state review
Summary
Board received a multi-school capital-project update covering the $56 million modernization program, school reopenings and elevator timelines, turfing of athletic fields, and concern that State Education Department review is slowing the high-school tech wing timetable.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Troy City School District board received a detailed update on the district's multi-year building modernization program, including reopening plans for School 16, turfing of athletic fields and delays in state review that could slow the high-school tech wing.
Mr. Hotaling, introduced by the chair as the presenter of the capital-project update, told the board the $56,000,000 modernization project was approved by voters in December 2019 and has proceeded in phases across elementary and secondary buildings. He reviewed completed work (windows and HVAC at Caroll Hill; the yearlong renovation at Detroit Community School) and recent openings, including completed Phase 3 work at School 18 that refreshed HVAC, secure entry and cafeteria spaces.
He said School 16 is in the tail end of a two-phase renovation and that students and staff are starting to move back in; furniture deliveries were under way the week of the update. "I don't think the elevator is going to be handed over to us for the start of school," Mr. Hotaling said, estimating it would be available about two weeks after school starts and adding that staff would address any ADA compliance issues at that time.
The board heard that the planned high-school tech wing (Phase 5) is still awaiting State Education Department engineering approval. "The queue is quite long," Mr. Hotaling said, and he urged accelerating design work to meet the goal of bidding and beginning construction in the coming school year. He said the new tech wing would be roughly 29,000 square feet and that building sequencing includes demolishing the old wing and creating linked circulation.
Mr. Hotaling also described site logistics: the old tech-wing footprint will become parking, and a temporary lot on a grassy area will be established during construction so events and day-to-day parking are preserved. He explained phasing challenges such as cutting over electrical and gas lines that currently feed the bridge connection to the tech wing before demolition.
The board was told smaller but consequential projects are funded from the general fund and through capital-outlay programs. Mr. Hotaling said School 12's HVAC work was finished in the prior fall and that related upgrades had federal capital-outlay funding (characterized in the meeting as a $5,000,000 capital-outlay transfer in May 2023). Athletic-field work at the high school (turf for softball and baseball fields) began in June with an October target for completion, and middle-school sewer-line replacement required removing and repairing a classroom floor because the pipe runs about 10 feet underground.
Mr. Hotaling flagged a second, separate package of work the board approved last May (referred to in the meeting as a $46,000,000 project, starting at Caroll Hill) and said SED approval timing is a concern for the team's planned schedule.
Votes at a glance - Minutes (07/31/2024): motion put on the floor; vote recorded as "Aye" in the meeting transcript; no detailed roll-call or tally provided in the transcript (motion recorded at SEG 679). - Consent agenda (multiple items across human resources, programs and business/finance): motions were put on the floor and the transcript records the board responding "Aye"; no detailed vote counts are provided (motions recorded at SEG 686, SEG 743, SEG 750).
Why it matters The modernization package affects multiple neighborhoods and school buildings, scheduling of classes and access (notably elevators and ADA compliance), and short-term parking and circulation during construction. State Education Department review timelines could delay the district's ability to bid and start the long-planned tech wing, potentially pushing construction into later seasons.
What's next Mr. Hotaling said the team will continue sequencing work, pursue SED approvals and manage temporary parking and staging plans as construction advances. The board also noted a ribbon-cutting for School 16 scheduled for the September meeting. The transcript does not record final dates for all milestones; several timelines (elevator handover, SED approvals) were described as estimates.