District reports capital‑project progress; board approves $165,283 roof change order
Summary
Administrators said summer phase‑2 capital work is on schedule, with 21 classroom spaces to be completed and boiler conversions and roofing underway; the board approved change order CG042 for roof replacement at the elementary school at $165,283 using project contingency funds.
Get email alerts on the Capital Project topic
No spam. Unsubscribe anytime.
District administrators reported progress on the summer phase of the capital project, saying contractors are on schedule and that 21 instructional rooms at the elementary school will be completed by the end of summer along with roofing work and a propane conversion for boilers.
An administrator said contractors have advanced framing, sheetrock and finish work in several classrooms and noted new single‑use restrooms and a custodial closet will be completed. The board’s facilities staff described planned hallway alterations and dedicated special‑education rooms created as part of the scope.
During action items the board approved change order CG042 to replace roof decking and the roofing assembly over two small elementary‑school rooms at a cost of $165,283. Administrators said the work responds to a persistent odor issue and involves full removal of layers (including an asbestos layer) and will carry a new 25‑year warranty; the cost will come from the project contingency.
Board members asked about other roofs and warranty coverage; administration said the issue was isolated to the affected section and contingency funds remain to complete the larger project. The board approved the change order by voice vote.