Board approves IEI contracts for Southwest High and Franklin Middle renovations
Summary
The board approved awarding IEI General Contractors two renovation contracts — $673,000 for Southwest High School gym/AV/bleacher upgrades and $739,000 for Franklin Middle School gym/AV/HVAC work — as part of referendum project rollouts; both motions carried with unanimous online votes.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Green Bay Area Public School District board approved two general-contractor awards on April 14, awarding IEI General Contractors the Southwest High School renovation contract for $673,000 and the Franklin Middle School renovation contract for $739,000.
Cale, the district project lead, told the board the Southwest work stems from the 2022 referendum and will focus on gym renovations, including the athletic floor, bleachers and AV equipment. For Franklin Middle School, Cale described the work as a gymnasium "refresh" rather than a full floor replacement, and said the package also includes HVAC upgrades and AV equipment in the auditorium.
Both motions were moved and seconded as part of the action items portion of the special meeting; the clerk announced online voting was open for each item and later confirmed the motions carried with all board members voting in favor.
These projects were presented as part of the district's ongoing referendum implementation and are scheduled to begin later this spring or early summer, with bidding and pre-construction steps already in progress for other referendum items.
Project funding: administrators tied both projects to previously approved referendum funding; no additional budget increases were requested at the meeting.
Next steps: the district will proceed with contractor coordination and scheduling; staff said work will be phased to limit classroom or extracurricular disruptions.