District construction update: contractors on site, gym expected around Christmas 2026 if schedule holds
Summary
A contractor update showed core contracts are in place and project spending is near $26.85 million; if bids and schedules hold the district could have $5–6 million in discretionary funds and expects to turn over a new gym around Christmas 2026, administrators said.
The Cuba City School District received a detailed update on referendum-funded construction and project scheduling at the board meeting.
Brad, identified in the meeting as the Epic representative working on the project, told trustees that early-phase contracts—excavation, concrete foundations, precast panels and major mechanical…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat