FEMA estimates $916,000 to shore Spanishburg school; board told floodplain permit required

Mercer County Schools Board of Education · November 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials said FEMA’s estimate to stabilize the Spanishburg school piling is $916,000 (excluding gym floor/finish work) and that floodplain permitting and a meeting with the county floodplain administrator (Keith Gano) are required before federal funds can move forward.

Miss Wellman, the district facilities representative, told the board that FEMA completed its initial claim for Spanishburg and reported a piling (peers) remediation estimate of $916,000. "That came in at $916,000," she said, and she emphasized that the figure does not include the gym floor and finishing work inside the building.

Wellman said FEMA asked the district to consult the county floodplain administrator, Keith Gano, and obtain any required floodplain permits before FEMA can proceed. "Our representative from FEMA wanted us before they will move any further on this project to meet with the floodplain administrator in our county, which is Keith Gano," she said. The facilities director also reported FEMA’s assessment that the site is effectively a floodway in practical terms, which limits mitigation options. "FEMA said there is really nothing we can do to mitigate that... it is a floodway, not just a flood plain," Wellman said.

Board members discussed possible structural measures and the cost‑effectiveness given the school’s size (reported enrollment: 159 students). The facilities staff advised that similar foundation and piling issues are expected at Princeton Primary and that comparable estimates may follow. The board asked staff to arrange a meeting with the county floodplain administrator and to report back with permitting requirements and options; President Prudich asked that the facilities director and superintendent meet with Mr. Gano and report findings to the board.