Construction managers report steady progress, outline $37,700 in near-term change orders and contingency usage

Elizabeth Forward School District Committee of the Whole · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction and facilities presenters reported progress on the high-school gym and auditorium, outlined multiple small change orders totaling about $37,708.15 if approved, and said the project still retains a multi-million-dollar contingency though about 27.5% of contingency has been used.

Construction and facilities staff gave the committee an on-site progress report and a rundown of proposed change orders on Oct. 8.

Dave Naciosi, the construction representative, said work is progressing in the gym and auditorium: painting preparation in the gym, slab-on-grade work in the auditorium, perimeter masonry, ongoing roofing and thin-brick installation in the gym lobby. He estimated the new lobby could open in six to seven weeks and said mechanical and plumbing work are advancing.

Facilities staff…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans