Construction managers report steady progress, outline $37,700 in near-term change orders and contingency usage

Elizabeth Forward School District Committee of the Whole · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction and facilities presenters reported progress on the high-school gym and auditorium, outlined multiple small change orders totaling about $37,708.15 if approved, and said the project still retains a multi-million-dollar contingency though about 27.5% of contingency has been used.

Construction and facilities staff gave the committee an on-site progress report and a rundown of proposed change orders on Oct. 8.

Dave Naciosi, the construction representative, said work is progressing in the gym and auditorium: painting preparation in the gym, slab-on-grade work in the auditorium, perimeter masonry, ongoing roofing and thin-brick installation in the gym lobby. He estimated the new lobby could open in six to seven weeks and said mechanical and plumbing work are advancing.

Facilities staff reviewed a set of potential change orders and potential change-order (PCO) items the district may request the board approve. The presenter listed mechanical items (two PCOs totaling roughly $4,332.76), a plumbing PCO of about $3,752.39, and a set of electrical PCOs (including a $9,044 wiring item, a $2,800 outlet installation and a $12,281.85 conduit upsize). When combined with other items the presenter said the four electrical items total about $29,623 and that bringing the full set forward would amount to roughly $37,708.15 for this period.

The presenter provided contingency figures: previously approved change orders totaled roughly $790,292.62; the original contingency was slightly above $3,000,000 and the presenter calculated that after the proposed items the contingency would be about $2,184,000 and that contingency usage stood at approximately 27.48% (change orders as a percent of total project cost at about 1.37%).

Staff said they would only submit change orders for board approval if they affected the project schedule; otherwise items would be brought to the board at the next regular meeting for ratification. Board members raised questions about gym-floor graphics, logo consistency with the football field, occupancy timing and drying time for finishes; staff said the floor graphics item is likely to be discussed at the November meeting given schedule constraints.

The committee received the update; staff said they would provide formal change-order documents by the end of day the following day for items needing immediate action.