Wilmette SD 39: 2023 chiller systems started; district honors retiring facilities lead

Wilmette School District 39 Committee of the Whole · April 15, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Nicholas and Associates reported chillers at four sites were started and will be commissioned once heating demand drops; the board also honored a retiring facilities leader for a long list of capital projects and improvements across district schools.

The Wilmette School District 39 Committee of the Whole received an update on 2023 facilities projects on April 15, including the startup status of newly installed chillers and next steps for commissioning.

Mike Bickler of Nicholas and Associates told the board the goal to bring all five chillers online at four locations over spring break was met. "We did successfully do that. So those chillers are, all started," he said, adding that final commissioning, test-and-balance work and district turnover will follow once buildings move out of heating demand.

District leaders also used the facilities item to recognize Colby on his upcoming retirement. The chair listed extensive contributions attributed to Colby, including learning-commons renovations across schools, multiple classroom additions, main-office renovations, air-conditioning installations at several buildings, science-wing additions, roof and boiler replacements, secure entry projects and other life-safety and infrastructure improvements. Board members thanked him for the work and presented small tokens of appreciation.

Next steps: presenters said commissioning work will continue as buildings shift into cooling mode and that systems will be turned over to district staff after test-and-balance and final commissioning procedures are complete.