Gwinn Area Community Schools bond plans add gym, 3,000‑sq‑ft CTE wing and secure health vestibule
Summary
Representatives and Integrated Designs reviewed bond-funded additions to the district’s middle and high schools: a new gym adjoining the athletic field with integrated concessions and toilets, a roughly 3,000‑square‑foot CTE/business wing, and a secure entry vestibule for the on‑site health center that serves people up to 27 years old.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
PJ introduced the meeting and said he was joined by Steve Boettcher of Integrated Designs to discuss planned modifications to Gwinn Area Community Schools’ middle and high schools under the district bond project.
Boettcher said the plan calls for a new gym sited beside the existing athletic field with a common entrance to create a unified sports complex. “First, we have a proposed gym that's going to be put on towards the athletic field next to the current gym with a common entrance for your sports complex of both gyms accessing that,” Boettcher said, adding the gym footprint will slightly intrude on the parking lot while still allowing circulation around the site.
He described the new gym as including a gate area to the ball fields and integrated concession and restroom facilities that will be built into the structure so they do not need seasonal draining and can support both outdoor field events and indoor gym use.
Boettcher said the district’s existing press box has been condemned and will be removed. “The concessions, the toilets, and the press box will have to be taken down and removed, and a new press box only will be put up since the toilets and concessions are part of the gymnasium addition,” he said.
The project also includes a roughly 3,000‑square‑foot addition for career and technical education (CTE) and business programs. Boettcher said the new CTE/business wing will be built adjacent to the existing trades facility because current classrooms in the academic wing lack the necessary volume for planned activities.
Finally, Boettcher outlined a security‑driven change at the health center: a small secure entry vestibule to separate health‑center visitors from the main school. “The health center services, people up to 27 years old, and currently, anybody up the street going to the health center has access into the school. We wanna make sure that is securely locked down and that people have to be buzzed into the school from the health center through that vestibule,” he said.
Boettcher closed by walking through the floor plan on the site map — pointing out locations for the gym, fitness/concessions/restrooms, the CTE/business wing near trades, and the secure health‑center vestibule — and thanked attendees. The provided transcript contains no formal motions, votes, or schedule for next steps.
Next steps: The transcript does not record a vote or formal decision; the items were presented as planned elements of the bond project.