Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Project topic

No spam. Unsubscribe anytime.

Hamilton Central hears $57M long‑range needs; board discusses $24M referendum timing

Hamilton Central School District Board of Education · August 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A consulting team updated the Hamilton Central School District board on roughly $57 million in identified capital needs and explained the district’s $24 million maximum cost allowance and recommended timing for a referendum to capture that allowance.

Chad Roberts, a consultant working with the district’s planning team, told the Hamilton Central School District Board of Education on Aug. 15 that a 2022 building‑condition survey and follow‑on long‑range planning exercise produced about $57,000,000 in potential work across district facilities.

Roberts said that the figure represents total identified needs, not the amount the district would ask voters to approve. “That $24,000,000 breaks down … about 19 and a half million in construction cost and about 4 and a half million of what they define as incidentals,” Roberts said, noting incidentals cover site work, soft costs, design and contingency. He added the $57,000,000 estimate includes major items such as a complete auditorium renovation (~$7.5 million), an “act suite” renovation (~$4.5 million) and a full primary‑wing upgrade (~$13.0 million).

Why timing matters: Roberts told the board the district’s maximum cost allowance (MCA) for the K–12 building will be available after Jan. 8, 2027, and recommended aiming for a March–May referendum to preserve the district’s full MCA. He warned that inflation and escalation were baked into current estimates — the figures include a 15% contingency and roughly 20% for incidentals plus an escalation allowance because bidding is likely to occur in later years. He also reminded members that approval must be followed by State Education Department (SED) review processes that can take many months; Roberts said some SED review windows approach seven to eight months.

Board members asked detailed questions about scope and phasing. When asked whether the auditorium figure included stage, curtains and lighting, Roberts replied: “That would be everything.” Board members and staff discussed prioritizing items that are near end of life (for example roofs or HVAC components flagged by the building‑condition survey) and phasing projects so critical infrastructure is addressed first.

Roberts also clarified the bus garage is not part of the $24 million MCA for the K–12 building. He said the garage is handled separately (he estimated roughly $5 million in that stand‑alone project) and that the district is weighing options including site work timing and EV bus readiness.

Next steps: The consultant said the district will continue refining scope, run cost scenarios in a shared prioritization spreadsheet and, if the board chooses to proceed, enter a pre‑referendum process that includes design, environmental review and voter outreach ahead of the proposed referendum window in spring 2027.