Mount Clemens officials to review waterfront and city hall RFPs, schedule interviews
Summary
At a Mount Clemens work session, staff said four proposals arrived for a waterfront parcel and encouraged commissioners to review submissions; an open design RFP for a city hall and fire station will be shortlisted and firms interviewed. The work session was adjourned to meet later for the regular meeting.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
A staff member told the Mount Clemens City Commission work session that four responses to the waterfront request for proposals (RFP) have been received and that the administration will circulate those proposals and the RFP criteria to commissioners for review.
"I will email those out to you. You can review them, and then we can discuss that at a future work session," the staff member said, urging an early review because proposals and quoted prices typically remain valid for about 30 days.
The staff member also described an open RFP for the design of a new city hall and fire station, saying the process will include department interviews and a public meeting and that the commission will approve each design phase. The presenter said about a dozen people attended a mandatory walkthrough and that the city expects at least six to eight proposals, with the RFP closing on the 13th, a Tuesday.
A commissioner asked that, when the administration shortlists firms, staff provide the selection criteria and a brief explanation if any firm is disqualified. The staff member agreed to provide that summary and proposed bringing the top three or four finalists to a work session for interviews and possible site visits.
The commission discussed public participation scheduling and confirmed there will be public input opportunities at the next regular meeting at 7 p.m., when the commission will also provide a brief slot for RFP respondents if needed.
Procedural action: a committee member moved to adjourn the work session; the motion was seconded by the chair and carried by voice vote. The commission adjourned and planned to reconvene at 7:00 p.m. for the regular meeting.
What happens next: staff will circulate the waterfront RFP responses and the RFP criteria to commissioners, arrange interviews with shortlisted design firms for the city hall/fire station project, and follow up with a work session to review recommendations.