High-school closeout stalls as PECO gas-line work delays intersection finish
Summary
District presenter Mr. Lynch said punch-list work at the new high school continues but a gas-line relocation on Red Lion Road controlled by PECO is delaying final paving and intersection 'masked arms' installation; the district is holding retainage and awaiting a PECO on‑site walkthrough.
Mr. Lynch, who presented the high-school project closeout, told the board the general contractor has finished many punch-list items but larger items remain, including millwork and the second elevator. "Schindler has been on-site this week working on that second elevator," he said, adding that mechanical, electrical and plumbing contractors are largely closed out and warranty items remain.
Lynch said the district has held significant retainage…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat