District says 7 Oaks project came in under budget but cafeteria equipment arrived damaged
Summary
The operations director reported the 7 Oaks construction project reached substantial completion at about 99.5% and that hard costs came in below the initial estimate; he also said $350,000 of kitchen equipment arrived damaged and negotiations with the vendor and manufacturer continue.
At the Lebanon Community School District 9 meeting the director of operations reviewed the 7 Oaks project closeout and a separate cafeteria equipment problem.
On the budget, he said the project’s hard-cost estimate was about $4,127,000 and reported, “we came in at $3,985,000,” describing the project as roughly 99.5%…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat