A space-needs study showed Health & Human Services has reconfiguration capacity (about 4,000 sq ft surplus), while administration and the judicial suite show deficits; consultants recommended phased master planning for a new justice center and noted replacement costs could exceed tens of millions.

Consultants presented a space-needs analysis for Richland County’s downtown services and told the Campus Reconfiguration Committee that some departments could be accommodated by reconfiguring existing space while court and jail functions will likely require larger, phased capital work.

Brian Nelson, principal designer with Venture Architects, said the Health & Human Services building across the street has about 25,340 square feet and, with reconfiguration, could yield roughly 4,000 square feet of surplus space suitable for relocating some county departments. "If this building was reconfigured in an ideal world, we actually do have a surplus of space... of about 4,000 square feet and change," Nelson said.

By contrast, the consultants reported that the county’s administration and judicial needs show deficits. The judicial suite lacks modern security circulation, jury deliberation spaces, and adequate ADA-compliant facilities; consultants invoked Wisconsin guidance (SCR 68) in explaining current courtroom shortcomings. "What Richland County has is... nowhere near hitting any of those marks," one consultant said, arguing that a new court facility (or significant renovation) should be considered as part of a master plan.

Consultants discussed master-plan approaches that phase work: build a law-enforcement center first (jail and sheriff’s office), followed by a judicial component that could be stacked above it to facilitate secure vertical transfer of defendants. They warned that full replacement of the courthouse block would be lengthy and expensive — one earlier ballpark estimate mentioned in the meeting was "north of $80,000,000." Consultants said they would include phased scenarios and cost estimates in the master-plan materials.

County supervisors asked for cost figures and timing; consultants said even a phased approach requires multi-year planning and that interim operational costs (for transportation if inmates must be housed elsewhere) should be accounted for. The committee asked consultants to circulate the analysis and plan for further board discussion.

The presentation concluded with an agreement to share plan PDFs and to schedule follow-up conversations with additional stakeholders.