OPM: school project nearing weather-tight stage as committee discusses tours, FF&E timeline
Summary
The owner's project manager and Alita reported exterior glazing, flooring and casework work moving quickly and said they expect to be weather-tight by year-end; committee members discussed tours, a meeting-schedule shift, and a public question about flag lighting and a nearby tower.
The owner's project manager told the School Building Committee that construction work on the new school is advancing across exterior and interior scopes and that the project is on pace to be weather-tight by the end of the year.
Alita, introduced by the OPM, described the near-term construction schedule: masons finishing brick work, glass installation following, roofing follow-up tasks, ongoing classroom and corridor flooring, installation of casework beneath classroom windows, and kitchen rough-in with one walk-in freezer already installed.
Why it matters…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat