School Building Committee approves $5.0 million phase 2 site work and several change orders
Summary
At a meeting of the School Building Committee, members approved ATPs including a $5,000,298.01 phase 2 base-bid site work package, a $19,378 display-case lighting install, and an $8,000 deduct for bollards; the owner's project manager reported the project is nearing weather-tight status.
The School Building Committee on an evening meeting approved several construction change orders, including a phase 2 base-bid site work package estimated at $5,000,298.01 that staff said is needed to achieve full certificate of occupancy.
The owner's project manager briefed the committee that finishes and flooring are being installed across the building, glass work outside the gym is in progress and site work is continuing; staff said they expect the exterior to be "buttoned up" and weather-tight by the end of the year. Alita, introduced by the OPM, detailed interior progress: classroom and corridor flooring installation, casework under classroom windows, kitchen rough-in and one walk-in freezer installed.
Why it matters: the phase 2 site work ATP covers remaining utility…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat