Summary

County staff updated the committee on multi-site radio tower construction (foundations and shelters installed, generators delivered), noted a delayed Yuba site due to lease/regulatory work, and confirmed a $224,000 PSAP grant payout and approved 2025 PSAP/GIS grants.

County communications and IT staff told the Public Safety Committee on Dec. 6 that the county’s multi-site radio tower project — authorized in 2023 — is advancing, with foundations in place, shelters erected and generators delivered to staging sites while one site (Yuba) has been delayed by leasing and regulatory work.

Staff said most tower sites are moving forward and that city utilities is temporarily storing generators. The committee was asked to review a fuller financial report at the Finance Committee meeting later the same day, where contingency and project finances will be discussed.

IT staff reported a $224,000 deposit from the 2023 PSAP grant and said the county’s 2024 GIS grant has begun spending; both the 2025 PSAP and GIS grants were approved and projects are planned to start in the next cycle. Staff also noted outstanding contract signatures from a major carrier (UScellular) are held in legal review and are delaying completion of some tower sites.

No formal committee vote on the radio project occurred in this meeting; staff invited committee members to join a Finance meeting for a full fiscal update.