Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Bridge topic

No spam. Unsubscribe anytime.

Consultants recommend replacing North Aberdeen Bridge unless $10 million in private funds are secured

Aberdeen City Council · June 27, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultants for the North Aberdeen Bridge presented three alternatives and said a federal $23.1 million grant funds design, right-of-way and construction work; stakeholders preferred salvaging the existing span but consultants said they will move forward with a full replacement (option 3C) unless roughly $10 million in private funding is secured to close the gap.

A consultant team led by David Evans and Associates told the Aberdeen City Council that a federal grant of about $23,100,000 will cover design, right-of-way acquisition and construction costs for the North Aberdeen Bridge project, but that estimated construction costs for the three shortlisted options range roughly from about $22 million to nearly $29 million.

Deborah Seaman, the consultant presenting the alternatives analysis, summarized the level-2 screening that advanced three options: two variations that salvage portions of the existing bridge (options 2A and 2B) and a replacement in the existing footprint that would allow elements of the old bridge to be repurposed in the adjacent park (option 3C). Seaman said stakeholder groups favored a salvage option (2B) but that preference was contingent on securing an additional private funding commitment of about $10,000,000. Without that private funding, the project team indicated they would move forward with option 3C as the preferred alternative.

Seaman said the study process included AutoCAD-based design concepts, construction feasibility reviews, environmental/permitting assessments and detailed cost estimates with contingencies. She described staging needs (temporary contractor access, work bridges and cranes), right-of-way impacts across a small number of parcels (option-dependent), and coordination needs with permitting agencies including the U.S. Army Corps of Engineers for river pilings and cultural-resource review.

Council members pressed the consultants on schedule and permitting. Seaman said the team’s goal is to obligate construction funding by Sept. 2026 — meaning right-of-way, environmental permits and project obligations would need to be in place by that date — and that environmental review is a major driver of the two-year-plus timeline to reach that point. On demolition, Seaman gave a ballpark figure of about $700,000 for the full-replacement option (3C), but noted that demolition and pilings work remain subject to permitting and further study.

The project team proposed forming a Kurt Cobain Memorialization Committee to engage community members and stakeholders on creative reuse of parts of the existing span if option 3C proceeds. No formal council vote on a final alternative was taken during the presentation; Seaman said the technical team would present the preferred alternative moving forward based on funding realities and permitting outcomes.

What happens next: the consultant team will continue design refinement, permitting and community outreach; council members and stakeholders signaled interest in remaining involved in outreach and in continuing to seek private contributions if salvage is preferred.