District official previews phased roof replacements and four bids for Phase 3; board weighs timing and capital constraints
Summary
District staff presented a phased roof-replacement plan (Phases 1–4) and four bids for Phase 3, including a TeamCraft quote (~$1.45M); the board discussed whether combining phases would save money but agreed capital constraints and transfer obligations limit doing multiple phases now.
A district official outlined a multi‑phase roof-replacement plan at the Nov. 18 work session and presented four contractor quotes for Phase 3, which covers about 34,600 square feet. The board discussed timing, per‑square‑foot cost increases and capital constraints that make doing multiple phases at once difficult.
The director described the phased map: Phase 1 (26,680 sq ft) and Phase 2 (27,750 sq ft) are complete; Phase 3 is 34,600 sq ft and Phase 4 is about 32,500 sq ft. He presented four bids for Phase 3: TeamCraft at…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat