Summary
Resident John Farrell asked the Town of Sunset Beach to schedule a presentation on the Jinx Creek and Toms Inlet study and to approve phase 2 work on a creek realignment, warning that a required one‑year bird study risks delaying permits if the winter season is missed; staff said materials were sent to council and staff will meet with CPE.
Get email alerts on the Coastal Projects topic
No spam. Unsubscribe anytime.
John Farrell, a Sunset Beach resident, told the town’s public input forum he is "really disappointed" the presentation of the update on the Jinx Creek and Toms Inlet study was postponed and asked the council to schedule the information "as soon as possible." Farrell said the study affects Palm Cove and "the whole East end of the island" and that residents want to educate the council and share concerns.
Farrell also urged approval of a coastal protection engineering (CPE) request for phase 2 of the creek realignment project, saying the first step is a one‑year bird study required before permits can be issued. "If they miss the winter season on that bird study, there's gonna be a big delay in getting those permits issued," he said.
The mayor and a staff member responded that presentation materials had been distributed to council members. The staff member said, "If the majority of the council wants to see that presentation, they'll inform me, and I can reach back out to you to to arrange that presentation," and noted a meeting with CPE was scheduled the following morning to discuss phase 2.
Why it matters: The study and the phase‑2 work relate to coastal realignment and permitting that can affect access and shoreline conditions on the island's east end, including Palm Cove. A missed seasonal window for the bird survey could delay permits for at least a year, residents warned.
What happens next: The staff member said they would reach out to arrange a presentation if the majority of council requests it; the scheduled meeting with CPE may inform next steps. The transcript does not record a council vote or formal direction on scheduling the public presentation.