Council asks for consolidated costs, tables two street‑engineering contracts

Roosevelt City Council · January 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Councilmembers asked staff to return with a single, consolidated project cost showing how engineering fees relate to overall construction estimates before approving two separate engineering letters; the council voted to table and requested the combined package be placed on the next agenda.

Engineers presented two related engineering proposals for street reconstruction, sewer (transite) replacement and resurfacing in the Bonnie Drive/1000 West and 100 South areas. Staff said the combined engineering proposals total approximately $192,100 and $67,500 for the two packages, while the previously discussed total project estimate was roughly $2.3 million and the work is already included in the budget.

Councilmembers stressed the need for a consolidated package that ties engineering fees to an overall project estimate and clarifies whether the work will be bid as a single prime contractor with subcontractors or as separate contracts. "It would be helpful in the future…if we have the project costs, anticipated project costs so we can see what the relationship is," the mayor said.

Several councilmembers recommended tabling the engineering approvals until staff combines the prior project estimate, the new engineering letters and the attachments into a single agenda packet so council and the public can clearly see what the engineering phase represents within the full construction budget. One council member moved to table and asked staff to return at the next council meeting with the consolidated materials; the motion passed after a second.

Council requested that the resubmittal include: the original project estimate previously presented to council, the current engineering‑phase fees, clear labels for which budget lines would cover which work, and contact/contract information for the engineering firms so council can confirm scope and deliverables.