Summary
The board opened four sealed bids for asbestos abatement at 116 and 130 South Pine Street, referred the bids to the facilities director, and later moved to award the combined contract to an Omaha firm (B2 Environmental Inc.) for a stated total of $34,700; the board recorded votes for the procedural motions but the transcript does not include a final roll-call tally for the award.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Hall County commissioners opened sealed bids for asbestos abatement at two county properties, 116 and 130 South Pine Street, reviewed four proposals, and referred the submissions to the facilities director for review. The clerk read line‑item pricing and days‑to‑complete for each bidder during the public opening.
Bidders and excerpted totals read aloud included Environmental Direct (Elva, Neb.), 2 Environmental Incorporated (Omaha), Horsley Specialties (Rapid City, S.D.), and Jamco Abatement (Waterloo, Iowa). The bid tab showed differences in scope pricing and proposed completion timeframes; one bidder proposed a notably higher aggregate price and longer timetable for completion than the others.
After the bid opening, a commissioner moved to accept the bids as read and refer them to the facilities director; that motion carried with the transcript recording seven yes votes. Later in the meeting a commissioner moved to award the asbestos‑abatement contract for both buildings to B2 Environmental Inc. of Omaha for a combined total of $34,700; that motion was seconded and the board proceeded with the question. The transcript records the motion and second but does not clearly record a roll‑call tally for the award vote in the public transcript excerpt available.
Commissioners and staff discussed whether the work could be awarded to different contractors for each building; staff said the procurement documents or scope may dictate a single award or separate awards depending on bidding instructions. Facilities staff will handle contract execution if the award is confirmed.
The procurement steps for asbestos abatement and demolition are part of the board's larger downtown‑building demolition and construction work, where commissioners also discussed timing, contractor scheduling and temporary parking impacts during construction.