Board reviews $75,000 settlement alignment and a $20,801.78 window change order for Wilson School

Sayreville Board of Education · January 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent reported the district is aligning finance paperwork with a $75,000 settlement with GreenSky and detailed a $20,801.78 change order for replacement window sashes at Woodrow Wilson School; the district reported $2,127 remaining in the referendum change-order reserve for that project.

The Sayreville Board of Education received an update on finance and infrastructure items including a settlement alignment and a window change order.

Superintendent Dr. Lavey told the board the administration is aligning paperwork with a settlement agreement involving GreenSky; the company is asking the district to sign bills of sale for installed and uninstalled equipment for the settlement amount of $75,000. The administration also presented a change order for replacement sashes at Woodrow Wilson School totaling $20,801.78.

Dr. Lavey said the referendum project account for the window work allows change orders up to $22,929 and that the district would still have $2,127 remaining in that account after the current change order. Board members asked what would happen if a future change order exceeded the remaining balance; Dr. Lavey answered the district would have to move funds from another bond referendum account and that doing so would require a formal board motion.

Discussion included standard budgeting practice of reserving a percentage of bid amounts to cover anticipated change orders. No formal vote on the settlement alignment or the change order is recorded in the transcript; the superintendent presented the items and answered board questions about funding and procurement process.

The board proceeded with routine approvals elsewhere on the agenda; administration said it would bring necessary motions forward for formal approval when contracts and final paperwork are ready.