Grosse Ile board approves bid awards and bid package for elementary renovations totaling millions

Grosse Ile Township Schools Board of Education · March 13, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Grosse Ile Township Schools Board approved staff recommendations to award multiple construction contracts for the Grosse Yale Elementary additions and renovations and passed a related bid-package resolution. The board heard staff say the recommended awards cover 17 of 28 bid categories and that redesigns and selective rebids aim to keep the project on budget.

The Grosse Ile Township Schools Board of Education on Thursday approved staff-recommended contract awards and a bid package tied to upcoming elementary renovations.

Board members heard a staff presentation that described a public bidding process that produced 79 proposals across 28 categories. Staff recommended awards for 17 categories, reporting a hard construction total of $8,844,228, construction management fees of $1,557,089 and a $728,092 construction contingency — a combined recommendation of $11,129,409 to move the project forward. Separately, the board approved a related bid-package resolution presented by staff with a reported grand total of $10,401,317 covering Park Lane scope items, staffing, general conditions, insurance, construction fees and contingency.

Staff said several large categories will be rebid and that redesign work, particularly on the roof, is intended to align the project with the district’s budget and schedule. "We feel that we have a very good plan in place to remedy these issues and continue the project and bring it in within budget," a district presenter said during the discussion.

The board voted by voice to approve the bid-package resolution and the staff recommendations; the vote was recorded as a motion, support and a unanimous voice "aye." The board did not record a roll-call tally in the public record during the meeting.

Board members and the buildings-and-grounds liaison reviewed committee vetting of bidder scopes, and the board asked for time to continue questions and review related materials. Construction management and the district’s architect remained available to answer technical questions as the project moves forward. The board indicated that rebidding certain categories and design adjustments are intended to reduce cost risk before final awards are executed.

Next steps described by staff include completing any rebid processes, finalizing contract documents for the recommended categories and continuing coordination with the architect and construction manager to maintain schedule.