Board reviews construction progress, approves operations building and portable-classroom contracts

Westfield-Washington Schools Board of Trustees · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction managers reported progress on the tennis center, transportation hub and several school-building projects; the board approved a $14.7 million Operations Building bid and purchased portable classrooms (approx. $1,032,009.84) to address near-term capacity needs.

Board members heard a series of construction updates and approved several capital contracts at the March 11 Westfield-Washington Schools meeting.

Core Construction’s representative (identified in the record as Chris) said the new Westfield Tennis Building has been turned over and is occupied after receiving a temporary certificate of occupancy Feb. 24; landscaping and entry signage remain and a ribbon cutting is scheduled for April 1 at 4:30 p.m. "The architect has walked through, verified all of our punch items have been completed," he said, while noting a small list of exterior landscaping and plaque work remaining.

Jonathan from Meyer Construction gave progress notes on the transportation building and the Town Road utility extension tied to that campus. Brian Kelly, the district’s director of construction, reported that the middle-school (Hagerman) foundations are about 60% complete and that other projects (Midland Crossing, Shamrock Elementary) have experienced permitting delays tied to utility and agency reviews; he said the team expected final utility approval soon but was in a third round of comments with Citizens/utility reviewers.

On motions, the board approved the Operations Building bid package at $14,700,000 (presented as under budget). The board also approved purchase of portable classroom pods to add temporary capacity: two pods at Monon Trail (four classrooms) and three pods at the intermediate (six classrooms). The winning portable bid was recorded in the meeting as about $1,032,009.84; the price includes purchase, delivery and required foundations, stairs and ramps, with additional district labor and site work to be performed separately. Administration said portables will be installed in June and ready for the first day of school.

Board members emphasized that portables provide short-term flexibility while the district proceeds with building openings and redistricting over the next school years. Construction leaders said they will continue to press schedules and monitor permitting.