Site superintendent says Page County Jail construction is moving toward finish as drywalling reaches about 75%

Page County Board of Supervisors · February 25, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Chris Volk, site superintendent for Samuel's Group, told supervisors that crews have installed rooftop HVAC units, completed much of the drywall, and expect detention frames to arrive between March 6 and March 9; exterior work including a generator pad pour is scheduled next week.

Chris Volk, site superintendent for Samuel's Group, told the Page County Board of Supervisors that construction at the county jail is advancing toward finishing work.

Volk said crews have been installing overhead conduit runs for data and electrical systems and are completing control wiring in detention frames. "I would say that we're 75% complete on drywalling and finishing," he said, adding that fire-stop work is largely completed and that drywall crews have been able to progress because insulation work is finished.

Volk described multiple trades working concurrently: electricians, sprinkler and HVAC contractors, and security installers. He said rooftop HVAC units went in last Monday and that roof exhaust fans are installed and being hooked up inside. WDSI is installing detention ceilings and the upper cell walls, and once the walls are in "the cells will be complete," Volk said.

On a timeline, he said detention frames were expected to arrive "somewhere between the sixth and the March 9," and that a contractor will pour the generator pad within the next week once frost comes out of the ground. He also said crews were beginning permanent exterior lighting and that painters are scheduled in March.

The superintendent pointed to project management tools and photos on Procore showing finished ceiling panels and said the site is transitioning from heavy infrastructure work to paint and finishes. He noted specific subcontractors by name during the update, including Graphite (detention frames), WDSI (ceilings and wall panels), Mahoney (main lines and branches), Cunningham, and Think Space (security wiring).

The report provided supervisors with the most recent timeline and immediate next steps: finishing detention frames and ceilings, completing interior utilities in cells, painting in March, and pouring the generator pad and exterior concrete and grading soon. The update closes a phase of mechanical, electrical and drywall work and signals the project is entering finishing stages.