Public works outlines seven grant projects and West Main rehab in Sonoma funding pitch
Summary
Public works presented seven priority projects for Sonoma County Transit and Climate Authority (SCTCA) Cycle 2 grants, including road rehab, sidewalk gap closures, bike boulevards and ADA ramp work; staff also updated the committee on the adopted capital improvement program and the West Main Street rehabilitation project timeline.
Get email alerts on the SCTCA Grants CIP Update topic
No spam. Unsubscribe anytime.
Public works staff on Aug. 4 asked the Traffic Safety Committee for feedback on seven priority projects the city plans to submit for Sonoma County Transit and Climate Authority Cycle 2 funding and provided a broader capital projects update, including near-term work on West Main Street.
Ashley (Public Works) said the grant round is competitive and the staff'recommended top-five priorities include road rehabilitation on 1st Street West, multi-street road rehab packages (Andrick, Murano, 7th Street), Broadway streetscape planning, sidewalk gap-closure planning, and a Newcomb Street road rehab/bike boulevard proposal. Staff said estimated project costs range from planning grants to multi-million-dollar construction requests and noted an earlier SCTCA award (Cycle 1) funded the "Go Sonoma" citywide bicycle and pedestrian improvements (CIPT 6).
On West Main Street (CIPT 11) staff said 90% design has been received from the consultant and that striping details (edge-lane striping) were added to address comments from a May traffic safety meeting; construction was estimated to begin in fall 2025 and finish before the rainy season. Staff also reported that removing a multiuse path from the Sasserina segment of CIPT 6 freed budget to add ADA improvements at several crossings.
Committee members asked about homeowner versus city responsibilities for sidewalk gaps; staff clarified sidewalk gap closures are typically planned through capital improvement projects while repair and trip-hazard maintenance on frontage are usually homeowner responsibilities, though the city sometimes grinds or performs interim mitigation and offers limited reimbursement programs.
Staff closed the CIP update by noting the traffic-calming handbook and the online traffic-hazard reporting form are now live on the city website and reminded the committee the next meeting is scheduled for Nov. 3.
Staff presented slides and estimates during the meeting and asked the committee to flag any feedback they wanted included in grant submissions due that Friday.