Board signs off on Mary Davis Home performance contract numbers and multiple construction bids
Summary
The board approved final bid tabulations and a performance‑contract amendment to move forward on the Mary Davis Home project, including individual subcontract awards and a pre-purchase of an HVAC condensing unit; one pre-purchase vote was 10–4.
Get email alerts on the Mary Davis Home Project topic
No spam. Unsubscribe anytime.
The Knox County Board approved final contract numbers and multiple subcontract bids tied to the Mary Davis Home performance contract on April 23, including carpentry, roofing, mechanical, electrical and technology/security packages.
Board members discussed the use of a performance contract model that assigns a general contractor administration fee (noted in committee at about 10 percent), bid tabulation details from the architect/engineer, and that some bid packages had single bidders. Bondi and other members explained the procurement and bid‑review process; Pam Davidson questioned how performance‑contract fees are applied and how bid tabulations were handled.
The board approved the individual bid awards and final payment draw requests, then approved an amendment to the master performance contract to insert the final approved amounts and authorize execution. That motion passed on roll call.
Separately, the board approved a pre‑purchase of one condensing unit for the Mary Davis Home at $28,700 to lock in current pricing; members debated refrigerant phase‑out issues and long‑term service/parts availability. The condensing‑unit pre‑purchase passed 10 ayes to 4 nays.
What happens next: the county will update and execute the performance contract with the final numbers, proceed with contractor scheduling and oversight, and coordinate a contractor administration process under the performance‑contract model.