Commission reviews fire-station contracts and several public-works projects

City Commission (City of Lake Wales) · November 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commission considered agreements and corrections related to Fire Station No. 3 (Colliers proposal, $166,004) and a scrivener's correction for the North Fire Station contract (total $767,024 including $251,703 alternate). Public Works presented tower painting, force-main engineering ($465,000), Basin 3 sewer rehabilitation design and a meter change-out program (approx. 1,600 meters).

City staff presented a cluster of capital and maintenance projects that the commission reviewed, including project management, contract clarifications and multi-year utility replacements.

Fire stations: staff described a proposed Colliers agreement for Lake Wales Fire Station No. 3 covering design, bid, construction and closeout phases with a total fee of $166,004 (15 monthly payments of $11,060.67). Staff also clarified a scrivener's error for a previously executed North Fire Station construction contract: the contract includes an alternate scope (expansion of the day room and apparatus bay) of $251,703; including that alternate, the contract sum is $767,024, below an original rough budget of $1.2 million.

Public works projects: Public Works Director Sarah Kirkland presented four items. First, exterior inspection, renovation and painting of the high-school elevated storage tower with a proposed price of $70,005.31. Second, a task order for Kimley-Horn covering engineering through construction administration for Force Main No. 1 improvements, estimated at $465,000. Third, a Basin 3 sewer rehabilitation program (staff described an estimated $7 million construction scale, with staff proposing to begin design and bidding for Basin 3). Fourth, a meter change-out program: staff estimated roughly 1,600 meters may be in need of replacement or upgrade and said the full eventual cost (if all ordered at once) would be close to $500,000; meter replacements are funded by utility fees, not general revenue.

Why it matters: the Colliers agreement moves design-phase management forward for a future fire station site the city bought in 2024, and the North Fire Station contract correction clarifies an already-executed contract's total. The sewer and meter programs affect operational capacity and billing accuracy; staff said meter failures can cause unbilled treated water and that replacing aging meters improves revenue capture and system capacity data.

Ending: Staff recommended approval or ratification where appropriate and indicated some items are corrections to previously executed documents; commissioners had routine questions on scope and funding and accepted staff's recommendations.