Wastewater director flags reservoir analysis and PFAS as CIP priorities; staff plans rate study

Sedona City Council · January 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The wastewater director told council that long‑term CIP drivers include capacity, disposal and aging infrastructure; staff flagged a 70M‑gallon reservoir breach analysis and possible PFAS removal as placeholders and said a wastewater rate study will start next fiscal year.

City wastewater staff outlined long‑term capital needs and signaled a near‑term funding and study schedule to support projects such as recharge wells and infrastructure rehab.

The director of wastewater said the city has completed many collection‑system and treatment‑plant upgrades since the 2018 master plan, but flagged outstanding items and regulatory uncertainties. “We are currently undergoing a reservoir dam breach analysis,” the director said, noting that the 70‑million‑gallon reservoir review could trigger additional improvements depending on the Arizona Department of Water Resources review.

Staff also identified PFAS monitoring and potential removal for liquid or solids as a regulatory unknown that could require future capital or operational investments. For financing, staff said the wastewater rate study will be advertised in spring (RFP) and begin in the next fiscal year; the study will present alternatives, phasing and the rate levels needed to fund both operations and planned projects.

For very large projects (tens of millions) staff indicated city cash could fund near‑term carryovers but that debt issuance (bonding) would likely be recommended once project costs exceed the practical pay‑as‑you‑go threshold.