Summary
Public Works officials told the Wallowa County commissioners that the 2026 road and maintenance budgets total about $37.39 million but project an $8.7 million year-end balance — short of a $10 million target needed for emergency response, local match and a project reserve.
Get email alerts on the Public Works Budget topic
No spam. Unsubscribe anytime.
Public Works Director Dan Mack, County Engineer Joel and Financial Manager Melissa Pike outlined the department’s 2026 spending plan and warned commissioners the county faces a structural shortfall that threatens capital work and routine maintenance.
Joel summarized how the department’s four funds fit together and said the County Road Fund’s total expense budget is $37,394,565. He told the board the department would like to hold a $3 million emergency response reserve and roughly $5 million in a project reserve so it can provide local matches for large grants. “In 2026, we would be gaining about $9 in outside funding for every dollar that we spend out of county road funds,” Joel said, describing a strong leverage effect but cautioning that the county must front-match many grants.
Mack described the department’s planned capital work, including a sand-shed and loader storage at Burbank and expansion of the Dell Avenue shop to add bays for vehicle maintenance. He also said the county will continue a chip-seal program, but with fewer miles next year (reducing from a current 60–67 miles to roughly 50) as a temporary measure to control costs.
Officials said the department’s projected ending balance for 2026 is about $8.7 million, under a $10 million target that would cover three months of operating costs, a $3 million emergency cushion and the $5 million project reserve. Joel and Mack urged the commissioners to consider incremental options — including the statutory 1% levy increase and state-level fixes to declining gas-tax revenue — while promising internal efficiency moves and smaller rate adjustments where possible.
Commissioners pressed the presenters on specific lines: questions included how many bridges $5 million in project reserve might fund (Joel estimated roughly four to five average county bridges with outside funding), whether a newly proposed chip-seal rotation would reduce safety, and how grant match timing affects cash flow. Diane, the county clerk, confirmed that an informational meeting with the assessor is scheduled to provide additional context for levy and rate options.
Next steps: Public Works will return with more granular numbers and the assessor’s guidance; the board set a public hearing date for levy/levy-rate decisions later in November.