Presenter says North Ridgeville high school project remains on schedule; foundations to start soon

North Ridgeville City Board of Education · March 5, 2026

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Presenters from the project team told the North Ridgeville City Board of Education the high school construction remains on schedule, early site work and the new transportation center are complete, demolition of an old maintenance building is underway and foundations work will begin by the end of the month.

A construction presenter and design representative updated the North Ridgeville City Board of Education on the new high school project at the board’s March 3 regular meeting, saying work through the winter kept the schedule intact and significant site preparation is complete.

The presenter (speaker 3) told the board that the early site work and the new transportation and maintenance center are complete, the building pad and underground conduit installation have been finished, and demolition of the existing maintenance building has begun. He said procurement of long-lead items and structural steel is under way and that foundations work is expected to begin by the end of the month. "We've been extremely active through the winter months," the presenter said. "We're right where we wanna be." (Presenter, SEG 089–SEG 109, SEG 200–SEG 206.)

Why it matters: the project’s sequencing is intended to allow interior work to proceed during inclement weather once primary structures are enclosed. The presenter explained the construction approach of dividing the overall high school into phases (referred to as Building A, B and C for sequencing), with Building A—most academic spaces—targeted first so interior work can continue while exterior work proceeds on later components such as the auditorium and athletics spaces.

The presenter summarized bidding and subcontracting activity, saying the team broke the overall project into 33 bid packages and received broad interest from subcontractors, and that subcontract awards are being finalized. He said crews will begin excavation and concrete foundations and that masonry and elevator towers will be among the first vertical elements. "We've taken the high school for construction purposes and divided it into buildings," he said. "We're gonna focus on the foundations for Building A." (Presenter, SEG 224–SEG 239, SEG 160–SEG 167.)

Board members asked about parking and fencing adjustments required for staging. A board member (speaker 5) asked whether the removal of fencing would affect the Bainbridge entryway; the presenter replied the main driveway will not be affected and that construction traffic will use a gated eastern access, with worker parking contained behind a fence and some temporary student parking later repurposed for construction staging. "That driveway will remain as is," the presenter said. (Committee member and Presenter, SEG 311–SEG 323, SEG 331–SEG 337.)

The design representative noted student engagement opportunities during construction and thanked community partners who participated in recent events showcasing career options for students. The board offered thanks to presenters and partners. The presentation concluded with the project team saying subcontract awards are proceeding and foundational work will begin in the coming weeks.

Next steps: the team will continue subcontractor awards, begin foundations work, procure structural steel and proceed with the phased sequencing described to the board. The board did not take any formal vote on the construction update during the presentation.