Board approves several change orders, amendments and a $1 million MAPS 3 allocation for Union Station

MAPS for Citizens Advisory Board · March 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At the March meeting the board approved multiple routine change orders and amendments across MAPS projects — Nash sidewalks ($502,360.42), Shiloh Southlake parks ($24,008.75), Rudy Innovation District ($86,694), Crossland Family Justice Center ($23,481) — and allocated $1,000,000 from MAPS 3 to Union Station renovations.

The MAPS for Citizens Advisory Board approved a package of routine items that included multiple change orders and an allocation of MAPS 3 funds for Union Station repairs.

Change orders and amendments approved by voice vote included:

• A $24,008.75 increase (Change Order No. 1) with Shiloh Enterprises for MAPS 4 Southlake Parks Improvement to reimburse permit billing and cover asbestos testing tied to demolition; the motion was approved by the board.

• Amendment No. 5 and Change Order No. 7 with Nash Construction for MAPS sidewalks and related amenities Phase 1a increasing the contract by $502,360.42. Staff said the increase covers concrete dye to blend with a historic area, cast‑iron tactile domes, sprinkler lines and meter boxes; a board member confirmed under‑run funds from earlier bids would cover the increase.

• Change Order No. 3 with Rudy Construction Company for MAPS 4 Innovation District connectivity Phase 1 increasing the contract by $86,694 to replace inlet grades for bicycle safety, rewire some traffic signals, add mass‑arm signage and account for calendar days at no cost.

• Change Order No. 5 with Crossland Construction Company for the MAPS 4 Family Justice Center increasing the contract by $23,481 to cover electrical adjustments, a chairlift power feed that was omitted from plans, additional communications cabling requested by police, and a brick alternate after the specified brick became unavailable.

The board also adopted a resolution allocating $1,000,000 from excess MAPS 3 capital improvement sales tax collections and/or interest to the Union Station renovation project to address HVAC, electrical and ADA issues and to improve main rooms. That resolution passed by motion.