Parents press district on field house mold and safety as board approves emergency roof replacement
Summary
Residents raised mold and safety concerns about Anderson Fieldhouse after flooding; the board approved an emergency roof replacement citing health and welfare authority and said a full renovation will be bid later this year.
Get email alerts on the Facilities Safety topic
No spam. Unsubscribe anytime.
Parents at the Summit Public School District board meeting pressed the district for clearer plans and remediation after heavy rain flooded the Anderson Fieldhouse.
Catherine Marks, who identified herself as a parent of two Summit High School students, asked why repairs were only now starting and raised concerns about mold: “Replacing the roof does not deal with the mold, and that's my biggest concern,” she said, and asked where the public could find the district's plan and remediation timeline.
Ed Fitzpatrick told the board he had observed rotting wood and missing gutters and asked the district to ensure the roof replacement is done as a permanent repair rather than a temporary patch. Sharon Trujillo, speaking as a resident and parent, asked what happens to standing water and whether the building had been inspected for structural or air quality hazards before students return.
Superintendent Scott Huff (transcript references also showed “Hough/Huff” in places) told the board the district secured county approval to proceed with an emergency roof replacement under emergency procurement rules invoked to protect student health and welfare. The board cited statutory emergency authority during discussion: “we were approved by the county to replace the roof through an emergency purchase in accordance with 18A‑18A‑7 which allows us, when it affects the health and welfare of a student, to do a project without having to go out to public bid,” a board speaker said.
Board members said the roof being installed now is the same roof planned for the larger renovation and that final renovation plans will be submitted for bid with an expected award later this year and construction to start in winter/spring 2025; the roof will remain in place during the full renovation. The board pledged to provide follow‑up answers to public questions about mold remediation and inspections and to share more details with concerned parents.
On the motion to approve the emergency procurement and related agenda items, the board recorded a roll call indicating unanimous approval by the listed members. The board also noted contingency plans for middle‑school facilities and other construction timelines during the school opening process.
Next steps the board mentioned included providing more detailed information to the parent who asked for follow‑up, completing the roof replacement (estimated to be watertight within about two weeks from the report), and moving ahead with the planned full renovation procurement schedule.
The board did not provide a public remediation timeline at the meeting; parents requested that the district follow up with inspections and remediation details before reopening spaces to student athletics and activities.