Coweta commissioners approve $365,000 in engineering amendments, reject unclear roof bids and approve filming closure
Summary
At the Jan. 6 meeting the board approved supplemental engineering agreements (East Aviation Way $85,000; US‑29 intersection $229,500; Fire Station 5 sewer design $51,420 with base design ~ $28,000), rejected two sets of roof bids over unclear bid sheets, and approved a temporary road closure for filming on Jan. 21.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Coweta County commissioners approved several contract actions and procurement decisions at their Jan. 6 meeting, advancing road‑and‑utilities projects while rejecting two unclear roof bids.
Public works administrator Todd Hanley (speaker S9) described staff recommendations for three supplemental engineering agreements. The board approved a supplemental agreement with American Engineers (doing business as STV) for design work to extend East Aviation Way at a cost of $85,000 to provide access to future terminal and hangar locations. Hanley also presented a staff recommendation to approve supplemental amendment No. 5 with the same firm for intersection improvements at US‑29 and Hal Jones/Greentop Road, citing a low proposal of $229,500 and the need for an ICE (intersection control evaluation) and coordination with the Georgia Department of Transportation; the board approved that amendment.
Hanley explained a proposed gravity sanitary-sewer connection design for the new Fire Station 5 to tie into Newnan Utilities. Integrated Science & Engineering submitted a proposal of $51,420, though Hanley said the base design is likely closer to $28,000 and that higher-cost line items listed in the proposal may be optional services; the board approved moving forward with design services.
On facilities procurement, Kelly Mickel (speaker S11) told commissioners that bid sheets for both the Madras gym and the work-release center roof replacement used a combination of total-price and per-square-foot entries that created inconsistencies across responses. Because the bids could not be compared on an apples-to-apples basis, staff recommended and the board voted to reject the submitted proposals and rebid both projects.
The board also approved a temporary closure of a portion of Luther Bailey Road on Jan. 21 for filming by Netflix/Amblin, subject to staff-recommended traffic windows (7 a.m.–7 p.m. filming with brief windows open for school traffic) and with off-duty deputies staffing the ends of the closure; Hanley confirmed the production agreed to the limited-open windows to reduce impact on Eastside Elementary. Finally, the board set a Feb. 12 work session at 9 a.m.
All votes on these items were taken by voice and recorded as carrying; no recorded dissents were shown in the transcript.