Pioneer Park P6 project advances; consultants outline design, floodplain findings and a roughly $5.3M price tag
Summary
Consultants told the Chena Riverfront Commission the Pioneer Park P6 package (boat launch, parking and Peggar Road path) clears floodplain analysis, includes landscape and circulation design, and carries a construction estimate near $5.3 million with phased work proposed for 2027–28.
Get email alerts on the P6 Pioneer Park topic
No spam. Unsubscribe anytime.
Consultants from Michael Baker International and Bettisworth North briefed the Chena Riverfront Commission on Jan. 28 about the P6 package: Pioneer Park boat launch and parking, vehicle plug-ins funded through congestion mitigation/air quality (CMAQ) funds, and the Peggar Road path alignment.
Project manager Sarah Shocker said designers completed hydraulic work and concluded the proposed footprint would not measurably raise flood elevation because of a local eddy at the site; she said the team expects a borough floodplain permit and that Section 4(f) evaluation is underway for impacts to recreational land. "We did all the detailed analysis to determine that, and we don't anticipate any problem obtaining a borough floodplain permit," Shocker said.
Shocker and landscape designer Ayesha Malik described design features intended to enhance access and resilience: a concrete non-motorized ramp (chosen for silt-prone conditions), relocation of the Wilderness Pavilion (to preserve the structure), a rain-garden swale for stormwater treatment, a visible bike rack and a bike-fix-it station, and a retaining wall design with the option of formed-concrete inset signage. "We're looking at about a 5,300,000.0 total construction cost," Shocker told commissioners.
Commissioners discussed circulation for Canoe Alaska access, trailer/launch expectations (design provides non-motorized launch, not trailer-based motor-boat ramps), vegetation and view impacts, and construction timing. Presenters said they aim to avoid multi-year park disruption and anticipate construction activities beginning in 2027 in phased work, with portions of site work potentially extending into 2028.
No formal action was required at the meeting; staff asked commissioners for feedback and said the next formal action item will be the local-planning approval packet, likely triggering a special meeting because of review timelines.