Hickory Creek Phase 3 delayed by railroad merger and gas‑line relocations; change order about $9M

Denton Public Utilities Board · February 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the PUB that Hickory Creek Road Phase 3 was delayed mainly by a railroad merger and conflicts with multiple natural gas lines; staff reported a change order presented to council of roughly $9 million and substantial completion targeted for April 2027 with final completion in May 2027.

The director of capital projects updated the Denton Public Utilities Board on Feb. 23 about Hickory Creek Road Phase 3, saying the project’s largest delay stemmed from a railroad merger and that work was also affected by multiple natural gas lines encountered during construction.

Staff said crews located and worked around lines operated by EnLink and a second operator in Eagle Ridge, and that one relocation effort was completed and the line is now out of service. The director told the board a change order was taken before council in May with a 'not to exceed' amount of roughly $9,000,000 to account for delays and relocations.

On schedule, staff reported substantial completion is expected in April 2027 and final completion in May 2027; they said traffic over the bridge could resume earlier, possibly by fall or winter of the same year as remaining work (sidewalks, punch list) is finished.

Board members asked whether the railroad conflict was the major cause of the three‑year delay; staff confirmed the merger of the two railroads was the principal driver of the delay. Staff also explained steps taken to clear drill shafts and pour caps to allow bridge beams to be placed and to remobilize drillers once relocations were finished.

Next steps: staff will continue to manage relocations, complete remaining drill shafts and provide updates to the board as the contractor progresses toward substantial completion.