Nampa staff report RAISE grant progress: multimodal projects advance, design and environmental steps ongoing

Nampa City Council · March 3, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff and HDR consultants reported that the $5 million RAISE program is advancing design and environmental work on eight projects across Nampa, with about 34% of budget spent to date and construction funding secured for at least one VRT‑funded project.

City staff and consultants briefed the council on implementation progress for a $5 million RAISE grant covering eight projects across the city.

Pearson DeWitt of HDR outlined the program schedule and design progress: multimodal repairs in North Nampa, mobility‑hub planning (75–80% complete), intersection improvements at Northside and 4th, 6th Street/2nd Avenue rehabilitation with new side paths, a feasibility concept for a 14th Avenue railroad pedestrian overpass, the eastern side path installation with a VRT‑funded construction allocation, a 1.6‑mile Indian Creek pathway concept and drainage/underpass work. DeWitt told council the environmental review has delayed some work but the team expects to wrap all projects by the prescribed end date.

Crystal Craig summarized budget and program status: about 34% of the grant budget has been spent while roughly 64% of scheduled deliverables are complete; the team intends to use all $5 million by the program end and to shift savings between subprojects as needed. Staff also provided a QR code linking to the RAISE public website for additional project detail and comment.

Council members asked whether VRT funding is secure for the eastern side path; staff said some design funds have been used and that construction funds are currently committed but could be contingent on future renewals. Council requested close coordination on timing and that staff pursue all reasonable opportunities to secure construction funding and accelerate where possible.

Staff will return with further technical milestones and public outreach dates tied to individual project phases.