Council authorizes $136,294.65 change order, extends Church Street contract 57 days

Paris City Council · February 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized a $136,294.65 change order adding three projects to the Church Street reconstruction contract with Richard Drake Construction — Washington Street resurfacing, paving and striping of a city-owned parking lot, and Hubbard Street mill-and-inlay — and granted a 57-calendar-day extension citing earlier wet weather delays.

The Paris City Council approved a $136,294.65 change order to the Church Street reconstruction contract with Richard Drake Construction and extended the contract by 57 calendar days.

Miss Easton, speaking for city staff, said the change order would roll three projects into the ongoing Church Street contract to avoid remobilizing a contractor. "The first is Washington Street... the second is the parking lot at the corner of Church and Kaufman... and then the third is a Hubbard Street project," she said, and added that rolling the work in provided better pricing and efficiency. She identified estimated amounts of roughly $65,000 for Washington Street and about $17,060 for the parking lot and said the Hubbard work required adding to an existing contract rather than competitively bidding it.

Council members asked whether available bond funds and the street fund would cover the work; Miss Easton said the Washington Street work would use funds already set aside in the street bond and that the Hubbard work would come from set-aside street maintenance funds. She also said contingency built into the Church Street project would not be exceeded by adding the work.

The chair moved to authorize the change order in the amount of $136,294.65 and a 57-day extension to the contract; the motion was seconded and approved by voice vote.