Finance panel recommends $1.23 million ordock electrical project despite budget shortfall; manager outlines funding plan
Summary
Manager reported the ordock electrical project is about $1.23 million (electrical bid $851,000; trench/earthwork $97,940; soil disposal $230,370; AT&T connection $50,000). Committee recommended approval with funding from remaining port revenue bond funds and port fund reserves; members raised safety, generator reliability and light-pollution concerns.
The finance committee recommended that the assembly approve the ordock (bridal) electrical project proposal in an amount not to exceed $1,229,310 after staff reported the project was under-budgeted and provided a breakdown of estimated costs.
Manager Emily Deetsch explained why the project came in over the prior budgeted amount: the electrical work had earlier been wrapped into a larger PPM scope and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat