Finance panel recommends $1.23 million ordock electrical project despite budget shortfall; manager outlines funding plan

Skagway Municipality Finance Committee · May 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Manager reported the ordock electrical project is about $1.23 million (electrical bid $851,000; trench/earthwork $97,940; soil disposal $230,370; AT&T connection $50,000). Committee recommended approval with funding from remaining port revenue bond funds and port fund reserves; members raised safety, generator reliability and light-pollution concerns.

The finance committee recommended that the assembly approve the ordock (bridal) electrical project proposal in an amount not to exceed $1,229,310 after staff reported the project was under-budgeted and provided a breakdown of estimated costs.

Manager Emily Deetsch explained why the project came in over the prior budgeted amount: the electrical work had earlier been wrapped into a larger PPM scope and mobilization and demolition costs were not reallocated when the electrical portion became a separate project, pushing the standalone price higher. Deetsch presented cost components: the electrical bid (Chet on Electric) negotiated down by $30,000 to $851,000; trenching/earthwork $97,940 (Hamilton proposal); soil disposal estimated at $230,370 (based on similar Ore Dock disposal costs); and an AT&T connection estimate of $50,000. Total estimated cost: $1,229,310.

Funding and safety: Deetsch said available funding sources include about $750,000 of remaining port revenue bond funds not otherwise obligated and port fund reserves for the balance; she said funding is available though the project exceeds the originally budgeted $350,000. Committee members stressed safety and reliability concerns, noting current generator problems and the need for adequate lighting and power for longshore operations; Deetsch and others said lighting options that reduce light pollution could be added and that engineers will consider covers or fixtures that direct light downward.

Committee action: The committee moved to recommend the ordock electrical project proposal to the assembly for approval at the stated not-to-exceed amount.